PROJECTS / WATER
Moka /Flacq District-2012
Proposed Pipeline from Pont Bon Dieu to Upper Parts of Lallmatie
Construction of 5 km of new HDPE water supply pipeline.
Proposed Pipeline from Pont Bon Dieu to Upper Parts of Lallmatie
Construction of 5 km of new HDPE water supply pipeline.
C2010/03: Proposed Pipeline from Pont Bon Dieu to Upper Parts of Lallmatie
Reference: STC 434
HDPE pipelines:
160mm Ø: 3200m
110mm Ø: 1200m
90mm Ø: 750m
N/A
Employer: CWA
Project Manager: CWA
Project Manager: Joseph Kong
Contract Manager: Maurice Hiu