PROJECTS / WATER

Moka/ Flacq-2014

Cote D'Or Integrated/Mixed Property Development Projects

The purpose of this project is to connect the sewer system of the new Cote D'Or Integrated/Mixed Property Development to an existing sewer system at Phoenix through about 3.5km of 400/500mm dia GRP pipeline and a new pumping station with 700m of 250mm dia. HDPE rising main.

  • Project Title

    PROJECT TITLE

    Cote D'Or Integrated/Mixed Property Development Projects - Offsite sewerage
     

  • Project Facts

    PROJECT FACTS

    Sewge pumping
    station:  1 no.
    400-500mm dia
    GRP pipe: 3,500m
    250mm dia HDPE
    pipe: 700m

  • Challenges

    CHALLENGES

    Management of changes in design.

  • Client Team

    CLIENT TEAM

    Employer: SIT Property Development Ltd
    Engineer: GIBB (Mauritius) Ltd

    SOTRAVIC TEAM

    Project Manager: Joseph Kong
    Contract Manager: Sheik Varsally