PROJECTS / WATER

Riviere du Rempart District-2011

Pumping Mains from Piton Bon Espoir

Construction of 3.2 km of new 250mm diameter DI water supply pumping main.

  • Project Title

    PROJECT TITLE

    C2010/17; Pumping Mains from Piton Bon Espoir to Poudre D'Or Balancing Tank
    Reference: STC 432

  • Project Facts

    PROJECT FACTS

    250mm Ø DI
    pipeline: 3200m

  • Challenges

    CHALLENGES

    N/A

  • Client Team

    CLIENT TEAM

    Employer: CWA
    Engineer: CWA

    SOTRAVIC TEAM

    Project Manager: Joseph Kong
    Contract Manager: Maurice Hiu