PROJECTS / WATER

Port Louis District-2015 – in progress

80,000m3 Water Treatment Plant

This Project is a Design-Build-Operate contract for the complete civil and electro-mechanical works for the rehabilitation and upgrade of an existing water treatment plant to produce 80,000 m3/day of potable water for the City of Port Louis; all whilst maintaining full operation of the plant. Works include the rehabilitation of existing slow sand filters and new construction of pre-treatment works, rapid gravity filters, backwash and chemical treatment plants and buildings, pump galleries and operations rooms together with connecting pipework, new road networks and replacement of the boundary walls. Contractor’s operation of the Plant is for a period of two years.

  • Project Title

    PROJECT TITLE

    Upgrading of Pailles Water Treatment Plant:
    Contract CWA/C2013/27
    Reference: STC 449

  • Project Facts

    PROJECT FACTS

    Project Duration: 20 months
    O & M: 24 months
    Contract Value: Rs 726 million
    Water Treatment 80,000 m3/d
    Concrete 6,800 m3
    Reinforcement 1,040 tons
    Pipework 1,200m
    Filter media 3,000m3

  • Challenges

    CHALLENGES

    Design and build the new treatment plant in a very tight schedule within the existing treatment plant while keeping the existing water treatment plant running

  • Client Team

    CLIENT TEAM

    Employer: CWA
    Project Manager: CWA

    SOTRAVIC TEAM

    CM: Maurice Hiu
    PM: Sheiland Malloo (Civil)
    Jean Pierre Wan (M&E)